Planning
Process
Given that the project would generate more than 50MW of renewable energy, Tillbridge Solar is classified as a Nationally Significant Infrastructure Project (NSIP). This means that we need to submit a Development Consent Order (DCO) application to the Secretary of State for Energy Security and Net Zero.
The Secretary of State will appoint an independent Examining Authority to scrutinise the development consent application in accordance with the relevant legislation (the Planning Act 2008). The Secretary of State will ask the Planning Inspectorate (PINS) to run the examination of the DCO application. Following this period of examination, PINS will make a recommendation to the Secretary of State as to whether to grant development consent.
You can read more information about the DCO planning process on the PINS website here.
The application for a Development Consent Order for Tillbridge Solar was accepted by the Planning Inspectorate on 9 May 2024. The application will now proceed to the next stage of the planning process.
Since our statutory consultation closed in July 2023, we have been reviewing all comments and suggestions and are continuing to have regard to this feedback. This has resulted in some minor changes to the draft Order limits which we consulted on as part of a targeted statutory consultation between 14 December 2023 and 25 January 2024.
A summary of the responses received throughout our pre-application consultation has been set out in a Consultation Report which can be accessed on the documents page on the Planning Inspectorate’s website here.
You are now able to register your interest in our proposals directly with the Planning Inspectorate, who will then inform you about the progress of our application during the examination process, and let you know about further opportunities you will have to inform and contribute to the planning process. You can register to take part in the planning process with the Planning Inspectorate here
Latest information on Cumulative Effects can be found in PEI Report Volume I Chapter 17: Cumulative Effects. This summarises our early-stage assessments and will be updated as part of our final Environmental Statement. All PEI Report chapters can be found in our ‘Documents Library’
Indicative timeline
- July 2022
- • Collaboration workshops held with stakeholders
- May to July 2023
- • Statutory consultation
- December 2023-January 2024
- • Targeted consultation
- Q1: 2024
-
• Preparation of DCO Application and associated documents including Environmental Statement
• DCO submission - Q2: 2024
-
• 28-day period for acceptance by PINS
• Pre-examination period (estimated to last up to four months), where stakeholders can register as an Interested Party - Q3–Q4 2024
- • Examination period by PINS on behalf of the SoS (estimated to last up to six months). The local community will be able to attend and take part in a series of hearings
- Q2: 2025
- • The panel of inspectors makes its recommendation to the SoS (within three months of the Examination concluding)
- Q3: 2025
- • Decision by the S0S to whether grant development consent (within 3 months of recommendation)
- 2025
- • Earliest construction date
- 2027
- • Earliest operational date